Critical Milestones

Gantt Chart

Refer to Gantt chart resources in the topic readings. Create a Gantt chart that displays 36 months, using the Office Timeline tool or any other tool to produce a Gantt chart. Be sure to include rational 1-36 months

Create a Gantt chart that outlines multiple critical milestones.

Summary

In a 250-300 word summary, address the following:

  • Include rationale for your Gantt chart.
  • Identify one critical risk you could encounter that could prevent you from meeting each of your goal/objectives.
  • Develop a contingency plan for the identified risk. Explain how this could maximize management efficiency and the allocation of resources. What leadership qualities are essential when dealing with the identified critical risk?

Provide three to five sources in your presentation.

This assignment uses a rubric. Please review the rubric prior to beginning the assignment to become familiar with the expectations for successful completion.

You are required to submit this assignment to Turnitin. Please refer to the directions in the Student Success Center.

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

Running Head: LIFE POINT EXPANSION GANTT CHART

Life Point Expansion Gantt chart
Name
Instructor
Institutional Affiliation
Date

1

LIFE POINT EXPANSION GANTT CHART

2

The Gantt chart presented for the Life Point Health expansion project highlights the
critical milestone to be achieved based on the expansion objectives. The project will run for 36
months approximately three years. This means that the project will include different activities
that are involved in the expansion of healthcare facility to improve on the level of service
delivery at the same time ensuring that the facility can meet the needs and expectations of many
community members in need of such critical services. The Gantt chart included various
milestones to be covered some of which included developing a strategic plan, initiating training
and development as well as identification of skill set that will be needed in the expansion of the
facility. The prototype of the facility must be developed based on the projected design which in
this case is one of the critical milestones highlighted in the project expansion Gantt cha...