Read the given short case (Javacom LAN Project) and then

1) identify 4-5 potential risk associated with the project.

2) for each risk you stated above, identify the Probability, Impact, and Mitigation.

Check the instruction file for detailed instruction and guideline.

Unformatted Attachment Preview

Instruction Read the case given above and do the following for the case. 1) 2) 3) 4) Identify 4-5 potential risks associated with this Javacom LAN project. For each risk, determine the probability of it happening and why. For each risk, determine the impact if the risk is realized and why. For each risk, identify the mitigation (ways to reduce the risk) of the risk. 1) Risk – Probability – Impact – Mitigation – 2) Risk – Probability – Impact – Mitigation – 3) Risk – Probability – Impact – Mitigation – 4) Risk – Probability – Impact – Mitigation – 5) Risk – Probability – Impact – Mitigation –
Purchase answer to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

1) Risk – The items with specific requirements could be hard to find.
Probability – 50% because certain types of specifications are not easy to find.
Impact – The delivery of the quality of the project could be compromised.
Mitigation – Identify a supplier who will look for and deliver all the specified items.

2) Risk – Underes...